Исполнительная документация по вентиляции | Перечень документов
top of page

The composition of the executive documentation for the section:
ventilation and air conditioning networks

1. Magazines:

   1.1. General work log

   1.2.  Journal of input quality control of materials

   1.3. Welding log (provided that these works were carried out)

   1.4. Journal of Concrete Works  (provided that these works were carried out)

   1.5. Cabling Log  (provided that these works were carried out)

2.  Certificates of examination of hidden  works :

   2.1.  Certificate of examination of hidden work for the installation of air ducts and valves

   2.2.  Certificate of examination of hidden works for the installation of fans, ventilation units

   2.3.  Device of passages of air ducts  through walls and partitions (sleeves, sealing)

   2.4.  Certificate of examination of air ducts hidden for dedusting

   2.5.  Certificate of examination of air ducts hidden for degreasing

   2.6.  The certificate of examination of hidden works on the fire protection device  air ducts

   2.7.  The certificate of examination of hidden works on the device of thermal insulation  air ducts

   2.8.  Certificate of examination of hidden works for the installation of passage nodes

   2.9.  Certificate of examination of hidden works for the installation of heat supply pipelines

   2.10.  The act of examination of hidden works on the device of openings (passages) through the wall,

        floors

   2.11.  Certificate of examination of hidden works for laying cables in pipes (sleeves)

3. Executive schemes:

   3.1. Executive scheme for laying air ducts (for each floor)

   3.2.  Executive scheme of equipment installation  (for each floor)

   3.3. Executive scheme for laying heat supply pipelines  (for each floor)

   3.4.  Executive scheme for laying power supply cables  (for each floor)

   3.5.  Executive scheme for laying cables of the automation system  (for each floor)

   3.6. Executive schemes for the device of passages through walls and ceilings

   3.6.  Executive schemes for the construction of foundations for equipment.

   3.7. Executive diagram of the device of the potential equalization system

4 . Test and acceptance certificates:

   4.1. Act of intermediate acceptance of critical structures

   4.2. Act of individual testing of installed equipment

   4.3.  Equipment acceptance certificate after comprehensive testing

   4.4. The act of measuring the thickness of the fireproof layer

   4.5. Acceptance certificate for completed fire protection works

   4.6.  The certificate of survey of networks of engineering and technical support

   4.7.  Act on flushing (purging) of heat supply pipelines

   4.8.  Hydrostatic or manometric leak test report

   4.9.  The act of checking devices and automation equipment

   4.10.  List of mounted devices and automation equipment

   4.11. Certificate of completion of commissioning

   4.12. Act of acceptance of the automation system

   4.13. Act of hydraulic tests

   4.14. Act on detected defects

   4.15. Act of transfer of equipment for commissioning

   4.16. The act of technical readiness of electrical work

   4.17. List of imperfections

   4.18. Schedule of deviations from the project

   4.19. List of installed electrical equipment

   4.20. Cable Inspection Protocol on the Drum

   4.21. The act of input control of materials

5.  Passports:

   5.1. Passport of the ventilation system      (Certification of ventilation systems in Chelyabinsk)

   5.2. Pipeline Passport

6. Programs:

   6.1. Integrated testing program ( download Example )  

   6.2. Acceptance testing program ( download Example )

7.  Certificates and passports of quality for the materials and equipment used,  sanitary and epidemiological conclusions, fire safety certificates

eight.  Operating Instructions  

9.  A set of working drawings for the construction of an object presented for acceptance, developed by design organizations, with inscriptions on the compliance of the work performed in kind with these drawings or changes made to them, made by persons responsible for the construction and installation works, agreed with the authors of the project

10. Work plan ( download Example )

* The list is based on  SP 73.13330.2016  "Internal sanitary systems of buildings" (SNiP 3.05.01-85)

** The presented composition of the as-built documentation for the section "Heating, ventilation and air conditioning" (HV) is approximate. The exact composition of the as-built documentation depends on the requirements of the customer.

The composition of the executive documentation for the section:
ventilation and air conditioning networks